- Location: The planning adjustment area is in Hong Ha commune, Dan Phuong district, Hanoi city.
- The boundaries and size of the land that do not change are determined by:
+ The North borders the residential area of Bong Lai village and the planned road is 20m wide.
+ The South borders the current canal and agricultural land.
+ The East borders the current canal and agricultural land.
+ The West borders the planned 18m wide road.
- Scale: 6ha.
– Adjustment of industrial land: The total area of industrial land before and after adjustment has no change in total area (remains the same as 33,043.50m2). In there:
+ Adjust the green tree strip between industrial land plots before adjusting CN01-CN02, CN03-CN04, CN05-CN06, CN07-CN08, CN09-CN10, CN11-CN12 into industrial land in industrial land plots with symbols CN01, CN02, CN03 after adjustment.
+ Adjust a part of industrial land area before adjustment from CN01 to CN12 into traffic land belonging to routes D1, route D4, route N1 and route N2 after adjustment.
+ Adjust route N2 before adjustment to industrial land in industrial land plots with symbols CN01, CN02, CN03 after adjustment.
+ Adjusted 12 industrial land plots before adjusting symbols from CN01 to CN12 to 3 industrial land plots after adjusting symbols CN01, CN02, CN03.
+ Adjusting the division of pre-adjustment industrial land lots with an area of 200-300m2 into post-adjustment industrial land lots with an area of ≥ 1,000m2.
+ Reason: According to Decision No. 33/2022/QD-UBND dated October 3, 2022 of Hanoi People’s Committee Promulgating “Regulations on management of industrial clusters in Hanoi city” Article 8: “… The minimum area for small and medium-sized enterprises, cooperatives, cooperative groups, household production establishments, and individuals in craft villages to rent for production and business is 1,000 m2 in craft village industrial clusters…” . Adjustments should be made to synchronize technical construction and ensure a minimum area to attract businesses, cooperatives, and business households according to regulations.
– Adjustment of green land: The area of green land and isolated green trees around the industrial cluster increased from 7,473.74 m2 to 9,539.40 m2 (adjusted to increase by 2,065.66 m2). In there:
+ Adjust a part of traffic land for routes N1, route D1, route N3, and route D4 before adjusting to green land CX01 and CX02 after adjustment.
+ Reason: adjust the green tree isolation strip around the industrial cluster with a width of ≥10m to ensure compliance with Regulation 01:2021/BXD.
– Adjustment of traffic land: Traffic land area decreased from 18,266.26m2 to 15,342.66m2 (adjusted down 2,923.60m2). In there:
+ Adjust the location of roads due to increasing the width of the green tree isolation strip.
+ Adjust route size:
* The entire internal road around the industrial cluster (section 3-3) removes the sidewalk on the isolated green tree row, adjusting the cross section from 11.5m (Broad=1.5m+3m; Side=2×3.5m) down 10m (Floor = 3m; Floor = 2×3.5m).
* Line D2 (from the main gate) Adjust the cross section from 13m (Bhe=2x3m; Side=2×3.5m) to 16.5m (Bhe=2x3m; Side=2×5.25m).
* Adjust N2 route (section 1-1) before adjusting it to industrial land.
– Adjustment of administrative and public land: Area reduced from 615.50m2 to 602.34m2 (adjusted down 13.16m2). Reason: Due to land plots being moved and changing areas, locally affecting the area of executive and public land.
– Adjustment of technical infrastructure land: Area increased from 601.00m2 to 609.62m2 (adjusted up 8.62m2). Reason: Because the land plots were moved and changed in area, locally affecting the area of technical infrastructure land.
– Additional adjustment of support service land: Addition of service support land located adjacent to administrative land with an area of 862.48m2. Reason: Adding service support land to support industrial and handicraft production in accordance with Decision No. 1292/QD-UBND dated March 14, 2018 of Hanoi People’s Committee.
Hong Ha Industrial Cluster project, located in Hong Ha commune, Dan Phuong district, Hanoi, is designed with an area of about 6 hectares and aims to develop industry in a sustainable and environmentally friendly form. school.
The project’s orientation is to build an industrial cluster according to “Green and Clean Industry” standards, ensuring energy saving, not polluting the environment and applying high technology. In particular, the project will also invest in an effective and advanced wastewater treatment and industrial waste collection system.
Along with building synchronous and modern infrastructure such as roads, warehouses, parking lots, gas stations, and electric charging stations, the project also complies with the principle of not arranging residential or storage units. residence, or commercial service center within the industrial cluster campus.
At the same time, ensuring environmental protection according to the provisions of Circular No. 31/2016/TT-BTNMT is also an important factor in the implementation of this project.
The Hong Ha Industrial Cluster project is set with a total investment capital of about 159.8 billion VND, to serve the relocation and expansion of production and business of small and medium-sized enterprises, cooperatives, and organizations. cooperation and production facilities of households and individuals in the region. This helps overcome environmental pollution, fire and explosion risks in residential areas and promote the development of local occupations and craft villages.